Premier Christy Clark and BC Hydro CEO Jessica McDonald at announcement to proceed with Site C dam on the Peace River, 2015. (BC GOVERNMENT)

$1.75 billion spent on Site C so far

BC Hydro details risks of delay with $60 million a month being spent

The Site C dam project in northeastern B.C. has spent $1.75 billion as of the end of May and is currently spending $60 million a month, BC Hydro CEO Jessica McDonald says.

McDonald and other BC Hydro executives briefed reporters Wednesday on the project, after an exchange of letters Tuesday between Premier Christy Clark, NDP leader John Horgan and B.C. Green Party leader Andrew Weaver.

McDonald provided details on Clark’s estimate that a delay in relocating two houses on the site on the Peace River near Fort St. John would create a “domino effect,” delaying construction of a realigned road and bridge that would lead to a one-year delay in diverting the Peace River to begin work on the dam foundation in the riverbed.

BC Hydro estimates show that delay would add $630 million to the cost of the project, including storage of turbines and generators, an additional year of site and environmental maintenance, and shutting down and restarting the main civil works contract.

McDonald said there is $4 billion spent or committed in existing contracts for the third dam on the Peace River, a system that already supplies a third of B.C.’s hydroelectric power. She would not comment on eventual costs of cancelling the project.

Horgan wants the Site C dam put to a review by the B.C. Utilities Commission. He said during the election campaign that does not mean stopping the project while the review goes ahead. After the minority government result and Weaver’s decision to support an NDP government, Horgan wrote to BC Hydro asking it to stop issuing new contracts and extend the lease on two houses set to be moved.

Weaver campaigned to have the project stopped. He attended the briefing at a Victoria hotel Wednesday, and said afterward the $4 billion cost estimate is a “gross exaggeration” based on the assumption all contracts would be paid out in full.

McDonald wouldn’t comment on the scenario of cancelling the $8 billion project, which she said is a political decision. Her presentation detailed the fallout from delaying the relocation of two houses for realignment of Highway 29 along the Peace River, a project about to be tendered by the B.C. transportation ministry.

The house properties have been expropriated and if they are not moved to make room for the two-year road and bridge construction, that would trigger a one-year delay in the river diversion needed to build the dam foundation in the main channel of the river.

Just Posted

Study shows special needs hard to meet in B.C. public schools

It’s lunch time at the Dunn-Reker house, and four happy children bounce… Continue reading

Fernie Museum fundraiser a blast from the past

Retro themed evening raises over $10,000 for museum programming

Fernie Alpine Resort opens for preview weekend

Fernie Alpine Resort will be opening for a preview weekend, this Saturday and Sunday

Local boys raise money for sick children in unconventional way

Four local boys have found a way to use their passion for… Continue reading

Skid Steer stolen from Sparwood Transfer Station

Elk Valley RCMP are seeking the public’s assistance with a theft that… Continue reading

VIDEO: Rare comic showing Superman’s 1st appearance to be auctioned

The 1938 comic features Superman hoisting a car over his head

Parastone weighs in on Slalom Drive

At a public hearing in Fernie Council on Tuesday night, Jacqueline Arling,… Continue reading

Ghostriders play hard against Nelson Leafs

Fernie Coach proud of team’s effort against top KIJHL contender

Cokato resident receives Order of Canada

Dr. Bryan Kolb has been instrumental in helping society understand what happens inside our heads

Mainroad discusses road conditions, standards

Last week, Mainroad, the Ministry of Transportation, the City of Fernie and… Continue reading

Dead rats on doorstep greets Summerland mayor

Two rodents have been delivered to Peter Waterman’s doorstep

Cougar confronts man in Clearwater

Clearwater resident Barry Joneson had a close encounter of the cougar kind

Panda picks Argonauts for the win

Giant panda at the Toronto Zoo picks Argos to win Grey Cup on Sunday

Most Read