Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Just Posted

Fires highlight need for more volunteers

Short-staffed volunteer fire departments in Elk Valley, South Country rely on mutual aid

Motorcyclist grateful to be alive, thanks fellow drivers

Over a dozen people stopped to assist Lori Hann after she tumbled off her bike on Hwy 3, Saturday

Local athletes ready for BC Summer Games

Twenty-four athletes from the Elk Valley and South Country will compete at the 2018 BC Summer Games.

GearHub staff staying positive after fire

Sporting goods store to fully reopen by end of July

UPDATE: New lead narrows the search for Serval cat

UPDATE, July 17: A new lead has narrowed the search for Aquila… Continue reading

BC Games’ Athletes Corner: What’s your favourite pump up song?

Check out what’s playing in the earbuds of BC Summer Games athletes before they compete

The Free Press editor wins awards

Editor Phil McLachlan has been recognized at the 2018 Canadian Community Newspaper Awards.

BC Wildfire update on Okanagan blazes

Watch the media briefing on the current fire situation in the Okanagan.

RCMP help to save goats from wildfire

The fast-approaching wildfire, sparked Thursday, forced the evacuation of five homes

VIDEO: Near drowning captured on popular B.C. river

Search and Rescue manager says the popular pastime of floating in the summer is inherently dangerous

Crosswalk vandalism leaves black mark for Cowichan as B.C. Games begin

Rainbow crosswalk defaced just days after being painted

Photo gallery: BC Games Day 1

A brief look at action from the 2018 BC Summer Games in the Cowichan Valley

UPDATED: Anti-pipeline campers digging in as eviction deadline expires

The City of Burnaby had ordered the Kinder Morgan pipeline protesters out for violating bylaws

Trump was taped talking of paying Playboy model: AP source

Source says former personal lawyer Michael Cohen secretly recorded discussion prior to 2016 election

Most Read