Slope stabilization work continues on the north bank of the Peace River for the Site C dam, September 2017. (B.C. Hydro)

UPDATE: Decision time for John Horgan on Site C dam

Energy Minister Michelle Mungall says delaying it is off the table

Premier John Horgan’s cabinet intends to make a decision on whether to continue building the most expensive construction project in B.C. history by the end of 2017.

The B.C. Utilities Commission released its independent report on the project Wednesday, ordered by Horgan to fulfil a promise he has repeated many times since becoming NDP leader.

The BCUC report questions whether Site C can make its 2024 completion date, and concludes the cost “may” exceed $10 billion. It describes the option of suspending work and restarting it in 2024 as the “least attractive of the three scenarios” set out by the government.

Energy Minister Michelle Mungall said Wednesday the report is technical and requires further study, but one thing that is clear is that delaying Site C is not an option that would protect B.C. Hydro ratepayers from unnecessary rate increases.

In the legislature Wednesday, Peace River South MLA Mike Bernier called on the government to make a decision within a month, to provide certainty to the people working at Site C. Eight years of study done under the B.C. Liberal government, and court decisions saying consultation with affected people was adequate, mean no further delay is needed, Bernier said.

Green Party leader Andrew Weaver said the report “should be viewed as the final nail in the coffin of Site C,” due to potential cost overruns and the B.C. Liberal government’s rush to secure fixed-term electricity supply to liquefied natural gas projects.

“The one issue of concern” is the transfer of the $4 billion cost of scrapping Site C to be added to the provincial debt, Weaver said.

Horgan’s government instructed BCUC to come up with cost estimates for completing the dam, pausing construction for a more thorough review of alternatives and future electricity demand, or stopping it and restoring the project area.

The report estimates the cost of shutting down Site C and remediating the project area to be $1.8 billion, plus the cost of finding alternative energy sources to meet demand, on top of the $2 billion already spent.

“The suspension and restart scenario adds at least an additional $3.6 billion to final costs and is by far the most expensive of the three scenarios,” the report states.

The BCUC panel also concluded that “increasingly viable alternative energy sources such as wind, geothermal and industrial curtailment could provide similar benefits to ratepayers as the Site C project with an equal or lower unit energy cost.”

Horgan said Tuesday that one more round of consultation with area Indigenous communities will be conducted next by Indigenous Relations Minister Scott Fraser, and then cabinet will consider its options.

B.C. Hydro has already awarded the major contracts for the powerhouse, river diversion and main civil works in the riverbed.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

B.C. freestyle skier wins gold

Cassie Sharpe of Comox shines in the halfpipe

22 teams compete in Sweetheart Curling Bonspiel

From February 9 to 11, the Sparwood Curling Club hosted it’s annual… Continue reading

Political theatre shines light on womens issues

The Vagina Monologues returned to Fernie last weekend for the second time,… Continue reading

Local rink heading to curling provincials

The Mens Masters East-West playdown took place in Sparwood from February 2-4.… Continue reading

Kootenay East MLA reacts to Throne Speech

Tom Shypitka says speech falls short of intended mark.

VIDEO: Traffic-sign abiding Fernie deer caught on tape

A herd of deer in Fernie, B.C. is getting attention online after stopping for a stop sign

How to keep local news visible in your Facebook feed

Facebook has changed the news feed to emphasize personal connections. You might see less news.

Virtue and Moir end ice dance careers with Olympic gold

Virtue and Moir’s gold medal win at the Olympics makes them the world’s most decorated figure skaters

Canadians find living in small spaces teaches creativity

Canadian families choosing to live in small spaces to bring closeness to children

NDP Health Minister calls to offer woman seat on Interior Health Board

Joyce Beddow-Buckland of Ashcroft was surprised by the call, and accepted the offer.

SAR suspends search for missing man at Sun Peaks

RCMP will continue to search for a missing man near Kamloops but SAR has suspended their role

Lottery will help save children’s lives

Each ticket gets you a chance to win a lot of money, while helping a lot of kids

B.C. RCMP officer officially cleared in car wash shooting incident

A report found the Salmon Arm officer fired 14 bullets at the man’s truck

Interest in Canadian Armed Forces remains high

Canada seeks about 5,000 recruits each year for its regular forces of about 68,000

Most Read