Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Mountain biker rescued

An injured mountain biker has been rescued by Fernie Search and Rescue.

Cameras to capture airborne dust

The District of Sparwood will install two cameras to document airborne dust caused by a nearby mine.

Housing affordability in spotlight

Elkford residents will soon learn the results of a survey on affordable housing for seniors.

Veteran golfer reflects on club anniversary

With a spring in his step, Patsy Caravetta hops up the steps… Continue reading

30 degrees and warmer forecasted with heat wave in B.C.

The weather could stay well into next week, according to Environment Canada

REPLAY: B.C. this week in video

In case you missed it, here’s a look at replay-worthy highlights from across the province this week

Former Penticton Vee recovering in hospital

Pittsburgh Penguin prospect expected to make full recovery

BC Lions defensive back Marcell Young levels streaker in home opener

Young hit the fan near one of the 45-yard lines

Police: Taxi driver who hit 8 Moscow pedestrians fell asleep

Two Mexican World Cup fans were among those hit

B.C. VIEWS: Orphans of our urban drug culture neglected again

Child advocate Bernard Richard leaves B.C. with harsh message

From marijuana beer to pot cookies, Canadian companies creating cannabis edibles

Manufacturers think that edibles will do well with users who don’t want to smoke or vape

Privacy lawyer warns against victim blaming in recent sextortion scams

Perpetrators get sexual photos of the victim and threaten to share them with friends and families

QB Jennings leads Lions to 22-10 win over Alouettes

B.C. wins CFL home opener over Montreal

Most Read