The expansion would triple Trans Mountain capacity to 890

PM approves Kinder Morgan pipeline, rejects Northern Gateway Trudeau government declares Trans Mountain twinning ‘safe for B.C.’

The Trudeau government has approved one controversial B.C. oil pipeline to the Pacific and rejected the second.

  • Nov. 30, 2016 8:00 a.m.

By Jeff Nagel

The Trudeau government has approved one controversial B.C. oil pipeline to the Pacific and rejected the second.

The federal cabinet today agreed to accept Kinder Morgan’s proposal to twin the 63-year-old Trans Mountain pipeline to Burnaby, and rejected Enbridge’s Northern Gateway oil pipeline across northern B.C. to Kitimat.

“If I thought this project was unsafe for the B.C. coast I would reject it,” Prime Minister Justin Trudeau said in Ottawa. “This is a decision based on rigorous debate, on science and on evidence. We have not been and will not be swayed by political arguments, be they local, regional or national.”

Trudeau said the decision complements the federal decision, supported by Alberta, to put a national price on carbon to help meet Canada’s international commitment to reduce greenhouse gas emissions.

He also said more pipeline capacity is needed to keep oil from travelling by rail across the country, at greater risk to communities.

“We have made this decision because it is safe for B.C. and it is the right one for Canada.”

Kinder Morgan’s $6.8-billion project would result in a seven-fold increase in tankers running through Vancouver harbour, carrying much more diluted bitumen than in the past.

Trudeau noted it’s the twinning of an existing pipeline that has been in operation since 1953.

In contrast, Northern Gateway would have been an all-new pipeline.

It’s the final nail in the coffin for the Enbridge project, that was widely considered dead in the face of widespread opposition from northwestern B.C. First Nations as well as the B.C. government.

Trudeau said the Great Bear Rainforest is no place for a pipeline and the Douglas Channel is no place for oil tanker traffic.

Enbridge’s $7.9-billion proposal, which had been in the works since 2005, had been conditionally approved by the former Conservative government in 2014, but that green light was overturned by a federal court ruling that the new Liberal government had already decided not to appeal.

The court had found Ottawa failed to meaningfully consult affected First Nations along the 1,177-kilometre route before approving the project.

Trudeau said the Liberal government will also fulfill a campaign promise to legislate a moratorium on crude oil tanker shipments on B.C.’s north coast.

The Kinder Morgan approval sets the stage for a massive confrontation with environmentalists in B.C.

Protesters have already been staging rallies and making preparations for what some believe will be a huge battle, perhaps rivalling the ongoing violent standoff over a pipeline project in North Dakota.

The expansion would triple Trans Mountain capacity to 890,000 barrels per day and result in a seven-fold increase in oil tanker traffic through Burrard Inlet to about 35 a month, which opponents say would greatly increase the risk of an impossible-to-clean spill of diluted bitumen.

Vancouver Mayor Gregor Robertson said he’s “profoundly disappointed” with the decision, calling it a “big step backwards for Canada’s environment and economy.”

Environmental groups aim to block any new pipeline to keep Alberta oil from being burned and contributing to climate change, and they were quick to slam the decision, calling it a “betrayal of promises.”

“Canadians — and especially British Columbians have said loud and clear that we don’t want this reckless pipeline coming anywhere near the Pacific coast,” Peter McCartney, Wilderness Committee climate campaigner, said in a statement. “To ignore the deeply held views of the vast majority of people who live on this coast is outrageous.”

McCartney said the tanker ban acknowledges that tankers pose an “enormous” threat to the coast. “If Justin Trudeau agrees that the Great Bear Rainforest is no place for a pipeline, he can’t possibly think that the Salish Sea is better.”

McCartney said more court cases against the projects are expected, and the decision is sure to be an issue in next spring’s provincial election.

The cabinet decision follows a ministerial panel review that earlier this fall flagged a series of unresolved questions over the project.

Those included whether the pipeline expansion can be reconciled with the Liberal government’s new climate change commitments, as well as aboriginal rights, particularly in light of Ottawa’s embrace of a UN declaration of indigenous rights.

That panel and other politicians have also urged Ottawa to consider forcing the pipeline’s new twin to bend south to a new terminal, at either Deltaport or Cherry Point in Washington State, to avert an increase in tankers through Burrard Inlet and minimize on-the-ground opposition in Burnaby.

The B.C. government has said the Trans Mountain proposal does not yet meet its five conditions for any new heavy oil pipeline.

Environment Minister Mary Polak said in a statement the province will continue to work to ensure those conditions are met.

She said Ottawa’s recent Oceans Protection Plan has gone further to address B.C.’s requirement for world-leading marine spill prevention and response.

Polak said the project has been under review for several months by the B.C. Environmental Assessment Office, which is soon to report.

“I have every confidence in B.C.’s environmental assessment process.”

Besides land and marine spill response and completion of environmental reviews,

Trans Mountain is also subject to 157 binding conditions set out by the National Energy Board.

Kinder Morgan aims to begin construction in September of 2017 and open the new pipeline in late 2019.

The company says the next steps following the federal approval include seeking all necessary permits, conducting a final cost estimate review with oil shippers who have signed onto the project, and a final investment decision by Kinder Morgan.

The Trudeau government also today approved the Line 3 pipeline upgrade by Enbridge from Alberta to Wisconsin. That $7.5-billion project will increase oil exports from 390,000 to 760,000 barrels per day and could be expanded further to 915,000 barrels.

Just Posted

CO Service euthanize emaciated black bear

The animal had left its den and taken shelter in a shed with cattle.

Local figure skater wins prestigious award

Sparwood’s Bree Chardonnens named B.C./Yukon STARSkate Athlete Of The Year

Fruitvale man identified in fatal zipline accident in Thailand

Spencer Donaldson, 25, was from Fruitvale, B.C., the city’s mayor has confirmed

Elk Valley water monitoring program expanding

Elk River Alliance to monitor Boivin and Coal creeks based on community feedback

Fruitvale man, 25, dies after falling from zipline in Thailand, reports say

Bangkok Post says man fell from Flight of the Gibbon zipline in Chiang Mai

4 victims killed in Penticton shooting spree remembered at vigil

John Brittain, 68, is charged with three counts of first-degree murder and one count of second-degree murder

GALLERY: Fernie Stoke Fest a smashing success

2019 event attracts sellout crowd to Fernie Community Centre April 6

Dedicated Sparwood volunteer honoured

Elk Valley Thrift Shop Society manager to receive 2019 BC Achievement Community Award

Three climbers presumed dead after avalanche in Banff National Park

One of the men is American and the other two are from Europe, according to officials

Two recommendations made in probe of B.C. train derailment that killed three

The CP Rail train went off the tracks near the B.C.-Alberta border in February

VIDEO: Trump tried to seize control of Mueller probe, report says

Special counsel Robert Mueller’s report revealed to a waiting nation Thursday

Short-circuit likely caused Notre Dame fire: police official

Investigators made an initial assessment of the cathedral but can’t yet search charred interior

Whitecaps fans stage walkout over club’s response to allegations against B.C. coach

Soccer coach has been suspended by Coastal FC since February

BC Ferries to pilot selling beer and wine on select sailings

Drinks from select B.C. breweries and VQA wineries will be available on the Swartz Bay to Tsawwassen route

Most Read