TIMELINE: Key dates in the history of the Trans Mountain pipeline

From 1953 to 2018, the Trans Mountain pipeline has been the way of transporting oil from Alberta to B.C.

Here are some key dates in the history of the Trans Mountain pipeline and Kinder Morgan Canada’s efforts to expand its capacity:

October 1953: The Trans Mountain pipeline begins shipping oil with an initial capacity of 150,000 barrels per day. The project features four pump stations along its 1,150-kilometre route and a marine dock that connects loading facilities on the east side of Edmonton with ocean tankers in Burnaby, B.C.

1957: Pipeline capacity is expanded via the construction of a 160-kilometre pipeline loop. The Westridge Marine Terminal is built and commissioned in Burnaby

Jan. 14, 1985: Trans Mountain’s biggest spill occurs at a tank farm in the Edmonton area. Nearly 10,000 barrels of oil are released.

2006 – 2008: The Anchor Loop project adds 160 kilometres of new pipeline through Jasper National Park and Mount Robson Provincial Park between Hinton, Alta., and Hargreaves, B.C. The extension includes 13 new pump stations and modifications to existing stations, increasing capacity from 260,000 bpd to 300,000 bpd.

Feb. 21, 2012: Kinder Morgan says it wants to expand the Trans Mountain pipeline after receiving support from oil shippers and will begin public consultations.

Dec. 16, 2013: An application is made to the National Energy Board (NEB) to expand the Trans Mountain pipeline. Construction is proposed to begin in 2017, with the aim of having oil flow through the expansion by December 2019.

November 2014: More than 100 people are arrested after they camp out in a conservation area on Burnaby Mountain, east of Vancouver, to block crews from conducting drilling and survey work related to the pipeline expansion. Most of the charges are later dropped.

READ MORE: Pipeline supporters rally across B.C.

READ MORE: Rival protests highlight B.C.’s divide over pipeline project

August 2015: The NEB postpones public hearings after striking from the record economic evidence prepared by a Kinder Morgan consultant who was to begin working for the regulator.

Jan. 12, 2016: Alberta Premier Rachel Notley says in a written submission to the NEB that the Trans Mountain pipeline expansion is in the best interests of both Alberta and Canada.

Jan. 27, 2016: The federal Liberal government says pipeline projects such as the Trans Mountain expansion will now be assessed in part on the greenhouse gas emissions produced in the extraction and processing of the oil they carry. Proponents will also be required to improve consultations with First Nations.

May 17, 2016: Ottawa appoints a three-member panel to conduct an environmental review of the Trans Mountain expansion project.

May 29, 2016: The NEB recommends approval of the pipeline, subject to 157 conditions, concluding that it is in the public interest.

Nov. 29, 2016: Prime Minister Justin Trudeau sanctions the Trans Mountain expansion, part of a sweeping announcement that also saw approval of Enbridge’s Line 3 pipeline replacement but the end of its Northern Gateway project.

Jan. 11, 2017: B.C. Premier Christy Clark announces her support for the project, saying Kinder Morgan has met five government conditions including a revenue-sharing agreement worth up to $1 billion.

May 15, 2017: The Federal Court of Appeal grants Notley’s government intervener status in a lawsuit filed by municipalities and First Nations against the project.

May 25, 2017: Kinder Morgan makes its final investment decision to proceed with the development, now estimated to cost $7.4 billion, subject to the successful public offering of Kinder Morgan Canada.

May 29, 2017: The B.C. NDP and Greens agree to form a coalition to topple the Liberal party, which won a minority government in an election earlier in the month. The parties agree to “immediately employ every tool available” to stop the project.

May 30, 2017: Kinder Morgan Canada debuts on the Toronto Stock Exchange after a $1.75-billion public offering.

June 29, 2017: The B.C. Liberals lose a no-confidence vote, clearing the way for NDP Leader John Horgan to become premier.

Aug. 10, 2017: The B.C. NDP government hires former judge Thomas Berger to provide legal advice as it seeks intervener status in the legal challenges against the project filed by municipalities and First Nations.

Oct. 26, 2017: Kinder Morgan Canada asks NEB to allow work to begin despite a failure to obtain municipal permits from the City of Burnaby.

Dec. 7, 2017: NEB allows Kinder Morgan Canada to bypass Burnaby bylaws.

Jan. 17, 2018: Kinder Morgan Canada warns the Trans Mountain expansion project could be a year behind schedule.

Jan. 18, 2018: NEB establishes a process to resolve permitting issues between Kinder Morgan Canada and provincial and municipal authorities.

Jan. 30, 2018: B.C. government moves to restrict any increase in diluted bitumen shipments until it conducts more spill response studies, a move that increases the uncertainty for Trans Mountain.

March 9, 2018: B.C. Supreme Court grants interim injunction aimed at preventing anti-pipeline activists from protesting construction at two terminals in Burnaby.

March 15, 2018: B.C. Supreme Court grants indefinite injunction preventing protesters from coming within five metres of two work sites for the project.

March 23, 2018: Green Party Leader Elizabeth May and New Democrat MP Kennedy Stewart arrested at a protest against the pipeline expansion; Federal Court of Appeal dismisses a B.C. government bid challenging a NEB ruling that allows Kinder Morgan Canada to bypass local bylaws.

March 27, 2018: City of Burnaby, B.C., says it will file an appeal to the Supreme Court in connection with the Federal Court of Appeal ruling.

April 8, 2018: Kinder Morgan Canada suspends non-essential spending on the Trans Mountain expansion project and sets a May 31 deadline to reach agreements with stakeholders.

May 29, 2018: Federal government announces deal to buy the Trans Mountain pipeline and expansion project from Kinder Morgan Canada for $4.5 billion.

The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

High school presents Alice In Wonderland

Since January the students, costume designers, set designers and musicians worked on this performance.

Boxers represent Fernie in Lethbridge

Two boxers from Fernie Old School boxing will be representing their mountain… Continue reading

Mountain biker rescued

An injured mountain biker has been rescued by Fernie Search and Rescue.

Cameras to capture airborne dust

The District of Sparwood will install two cameras to document airborne dust caused by a nearby mine.

Homeless people living on ‘Surrey Strip’ move into modular housing

BC Housing says 160 homeless people are being moved into temporary Whalley suites from June 19 to 21

Port of Prince Rupert names Shaun Stevenson as new CEO

Stevenson has worked for the port for 21 years as vice president of trade development

Senate officially passes Canada’s marijuana legalization bill

Bill C-45 now moves to royal assent, which is the final step in the legislative process

Fake attempted abduction not funny to B.C. neighbourhood residents

Two teenage boys won’t face criminal charges after scaring girl

Mosquitoes out in full force already? Blame the weather

But a B.C. mosquito expert says the heat wave will help keep the pests at bay

Man pleads not guilty in 1987 slayings of B.C. couple

William Talbott of SeaTac was arraigned Tuesday in Snohomish County Superior Court

New GOP plan: Hold kids longer at border – but with parents

Move would ease rules that limit how much time minors can be held with their parents

Without a big data strategy, Canadians at risk of being ‘data cows’

Presentation said artificial intelligence could give Facebook and Amazon even more power

Five B.C. families stuck in Japan as Canada refuses visas for adopted babies

Lawyer points to change in American policy around adoptions from Japan

Most Read