Four new storage tanks have been constructed at Trans Mountain’s Edmonton terminal to prepare for opening of the oil pipeline expansion from Alberta to Westridge Terminal in Burnaby B.C. (Trans Mountain)

Trans Mountain begins laying Alberta pipeline for expansion

Construction continues at Westridge terminal in Burnaby B.C.

Trans Mountain Corp. has begun laying pipe across the Alberta segment of its oil pipeline twinning project, expecting to have the first pipe welded, tested and buried by Christmas.

Construction so far has included completion of four new storage tanks at the federal government-owned company’s Edmonton Terminal, and continued work on the Westridge Terminal facilities at Burnaby to accommodate additional tankers for exporting crude.

Pipe is being assembled on the Greater Edmonton section, with clearing, grading, utility relocation and worksite preparations for a series of tunnel-bored sections. Horizontal drilling is planned for 13 sections on the Alberta side of the project, to cross watercourses, railways, major roads, sensitive environmental areas and urban areas, Trans Mountain said in its latest project update.

Trenchless construction is also expected to play a large role in the B.C. section of the project, where thousands of property owners have moved in along the right-of-way since the original Trans Mountain was built in 1954.

Trenchless construction is also expected to play a large role in the B.C. section of the project, where thousands of property owners have moved in along the right-of-way since the original Trans Mountain was built in 1954 to supply refineries at Burnaby and Washington state as well as tanker exports from Burnaby.

RELATED: CEO promises ‘the best darn pipeline in the world’

RELATED: Indigenous leaders choose pipelines over poverty

RELATED: Oil-by-rail traffic rises as B.C. battles Trans Mountain

The B.C. government has continued to oppose the Trans Mountain expansion, supported by Washington Gov. Jay Inslee, despite increased crude by rail coming through Alberta and B.C. to Washington since the existing Trans Mountain line became over-subscribed.

In a year-end interview with Black Press, B.C. Premier John Horgan acknowledged that construction is likely to intensify an already acute shortage of skilled construction workers, as work camps and gas pipeline spreads take shape across northern B.C. to supply the LNG Canada project from Dawson Creek to Kitimat.

B.C. is using a union-only construction model to build the Kicking Horse Pass and other sections of the Trans-Canada Highway from Kamloops to the Alberta border, as well as replacing the Pattullo Bridge and building the Broadway subway line in Metro Vancouver. A skilled labour shortage is driving up costs on those projects, Horgan said.

“And at the same time we have private sector projects like LNG Canada, and potentially the Trans Mountain pipeline, that are going to be taking a whole bunch of workers out of play when it comes to public contracts, and that’s a challenge for government,” Horgan said.

From the Greater Edmonton section, the Trans Mountain right of way goes to Edson, Hinton, Spruce Grove, Stony Plain and Wabamun before reaching the Jasper-Mount Robson stretch where twinning was done a decade ago.

Entering B.C. in the North Thompson region, the pipeline route goes by Avola, Barriere, Blue River, Clearwater, Valemount and Vavenby, where the forest industry has been wound down due to market conditions and loss of lumber to beetle infestations and fires.

At West Barriere, another existing expansion section will be tested and activated, running from a pump station north of Barriere to a new Black Pines pump station north of Kamloops. From there the project goes past Kamloops and Merritt, then down the Coquihalla Pass to Hope.

The project proceeds down theFraser Valley through Chilliwack, Abbotsford and Langley, then into the heavily populated Lower Mainland through Langley, Surrey, Coquitlam and Burnaby.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureTrans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

NDP headquarters on election night, Oct. 24, 2020. (Katya Slepian/Black Press Media)
ELECTION 2020: Live blog from B.C. party headquarters

BC NDP projected to win majority government – but celebrations will look different this election

Tom Shypitka, pictured with his campaign team. on election night, Oct. 24, 2020. Trevor Crawley photo
Updated: Shypitka wins second term; BC NDP cruise to majority

“Election Days,” rather than “Election Day,” may be the more accurate term… Continue reading

B.C. Green Party leader Sonia Furstenau outlines her party's climate action platform at Nanaimo's Vancouver Island Conference Centre earlier this month. (News Bulletin file photo)
Green leader Furstenau declared victor in her home riding on Vancouver Island

Cowichan Valley voters elect freshly minted party leader for her second term

John Horgan has been re-elected the MLA for Langford-Juan de Fuca. (File-Black Press)
Horgan trounces challengers to be re-elected in his Vancouver Island riding

MLA has represented constituency of Langford-Juan de Fuca and its predecessors since 2005

BC ELECTION
Voting day: Elk Valley braves the cold to vote for next MLA

Today is the last chance for voters to have their say

NDP Leader John Horgan celebrates his election win in the British Columbia provincial election in downtown Vancouver, B.C., Saturday, Oct. 24, 2020. THE CANADIAN PRESS/Jonathan Hayward
Horgan celebrates projected majority NDP government, but no deadline for $1,000 deposit

Premier-elect says majority government will allow him to tackle issues across all of B.C.

NDP Leader John Horgan speaks with the owner of a barber shop while campaigning in Pitt Meadows, B.C., on Friday, Oct. 16, 2020. Campaigning was restricted by the coronavirus pandemic. THE CANADIAN PRESS/Darryl Dyck
Horgan’s B.C. majority came with historically low voter turnout

Barely half of eligible voters cast ballots in snap election

A Cranbrook mother is receiving praise across the world for her design of a sensory path aimed at helping kids in school when they need a movement break. (Chantal Marra file)
Cranbrook mother receives international praise for sensory paths business

Chantal Marra has sold her sensory path packages to schools across the world

A police pursuit ended with an arrest in Williams Lake on Highway 97 Sunday afternoon. (Facebook video screenshot)
Video catches police pursuit that ends with man kicked, punched in Williams Lake

A video of the arrest is getting widely shared on social media

Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

FILE – Prime Minister Justin Trudeau greets Premier John Horgan during a press conference at the BC Transit corporate office following an announcement about new investments to improve transit for citizens in the province while in Victoria on Thursday, July 18, 2019. THE CANADIAN PRESS/Chad Hipolito
Trudeau congratulates Horgan on NDP’s election victory in British Columbia

Final count won’t be available for three weeks due to the record number of 525,000 ballots cast by mail

Comedic actor Seth Rogen, right, and business partner Evan Goldberg pose in this undated handout photo. When actor Seth Rogen was growing up and smoking cannabis in Vancouver, he recalls there was a constant cloud of shame around the substance that still lingers. Rogen is determined to change that. (Maarten de Boer ohoto)
Seth Rogen talks about fighting cannabis stigma, why pot should be as accepted as beer

‘I smoke weed all day and every day and have for 20 years’

Provincial Green Party leader Sonia Furstenau speaks at Provincial Green Party headquarters at the Delta Victoria Ocean Pointe in Victoria. (Arnold Lim / Black Press)
VIDEO: Furstenau leads BC Greens to win first riding outside of Vancouver Island

Sonia Furstenau became leader of BC Greens one week before snap election was called

NDP Leader John Horgan elbow bumps NDP candidate Coquitlam-Burke Mountain candidate Fin Donnelly following a seniors round table in Coquitlam, B.C., Tuesday, October 20, 2020. THE CANADIAN PRESS/Jonathan Hayward
Horgan, NDP head for majority in B.C. election results

Record number of mail-in ballots may shift results

Most Read